Default Estimate vs Quote

As title. Whatís the difference.

I stupidly gave a family friend an estimate to dig out an area for them to build a small block of stables (husbands a general builder). And thought I could do with a bit of fill so was thinking along the lines of cost of fuel and machinery with a little on top. Itís roughly 500t of Clay being cut out of a 55degree slope. Iíve had a few hitches with my kit when the first cold blast came over so hired in some. Itís taken over 3 days to dig and cart out and itís only done about 3 quarters. So I reckon a day more. Anyway they keep moaning about it and want it done yesterday. I said itís gone about £500 over what I thought it would cost and the guy has flipped saying I quoted x amount and they only budgeted that much for it (wife probably wants to spend it elsewhere on stables).

I only sent them a text estimating how much and how long itíd take.

Whatís your thoughts?
Reply With Quote
  #2   IP: 83.197.102.226
Old 23-03-2018, 10:07 PM
furniss480 furniss480 is offline
Master Elect of Nine
 
Join Date: Jan 2012
Posts: 466
Default Re: Estimate vs Quote

Dont work for family and friends
Reply With Quote
  #3   IP: 31.51.59.42
Old 23-03-2018, 10:09 PM
V8Druid's Avatar
V8Druid V8Druid is offline
Knight of the Rose Croix of H.R.D.M
 
Join Date: Jun 2013
Location: Druid central, just East of Pandy, Nr. Abergavenny, S. Wales, UK, 3rd rock from the Sun
Posts: 15,034
Default Re: Estimate vs Quote

Quote:
Originally Posted by peterpecker View Post
As title. Whatís the difference.

I stupidly gave a family friend an estimate to dig out an area for them to build a small block of stables (husbands a general builder). And thought I could do with a bit of fill so was thinking along the lines of cost of fuel and machinery with a little on top. Itís roughly 500t of Clay being cut out of a 55degree slope. Iíve had a few hitches with my kit when the first cold blast came over so hired in some. Itís taken over 3 days to dig and cart out and itís only done about 3 quarters. So I reckon a day more. Anyway they keep moaning about it and want it done yesterday. I said itís gone about £500 over what I thought it would cost and the guy has flipped saying I quoted x amount and they only budgeted that much for it (wife probably wants to spend it elsewhere on stables).

I only sent them a text estimating how much and how long itíd take.

Whatís your thoughts?
ask them to show you your written quotation ..... an estimate is just that .... your best guess/estimated cost, of the job.

A quotation is effectively a contract to carry out the works for a fixed price
__________________
If it's got tracks, wheels, t*ts, or an engine, at some point it's gonna give you trouble!!
To view links or images in signatures your post count must be 10 or greater. You currently have 0 posts.
Reply With Quote
  #4   IP: 31.51.59.42
Old 23-03-2018, 10:10 PM
V8Druid's Avatar
V8Druid V8Druid is offline
Knight of the Rose Croix of H.R.D.M
 
Join Date: Jun 2013
Location: Druid central, just East of Pandy, Nr. Abergavenny, S. Wales, UK, 3rd rock from the Sun
Posts: 15,034
Default Re: Estimate vs Quote

Quote:
Originally Posted by furniss480 View Post
Dont work for family and friends
was about to edit my post saying exactly that .... and never sell anything to them either
__________________
If it's got tracks, wheels, t*ts, or an engine, at some point it's gonna give you trouble!!
To view links or images in signatures your post count must be 10 or greater. You currently have 0 posts.
Reply With Quote
  #5   IP: 31.52.68.248
Old 23-03-2018, 10:12 PM
peterpecker peterpecker is offline
Secret Master
 
Join Date: May 2011
Posts: 84
Default Re: Estimate vs Quote

I thought as much but they were adamant and it was getting heated on the phone.
Reply With Quote
  #6   IP: 31.52.68.248
Old 23-03-2018, 10:13 PM
peterpecker peterpecker is offline
Secret Master
 
Join Date: May 2011
Posts: 84
Default Re: Estimate vs Quote

Quote:
Originally Posted by V8Druid View Post
was about to edit my post saying exactly that .... and never sell anything to them either
Donít I realise that now! When I thought I was being a nice guy too
Reply With Quote
  #7   IP: 81.147.100.200
Old 23-03-2018, 10:18 PM
hiluxman hiluxman is offline
Elect of Fifteen
 
Join Date: Jul 2015
Posts: 734
Default Re: Estimate vs Quote

Quote:
Originally Posted by V8Druid View Post
was about to edit my post saying exactly that .... and never sell anything to them either
Yes it's better to fall out for a few days for saying no than fall out for a lifetime over something daft that goes wrong, which is no ones fault.
__________________
If in doubt hit it.
Reply With Quote
  #8   IP: 31.51.59.42
Old 23-03-2018, 11:30 PM
V8Druid's Avatar
V8Druid V8Druid is offline
Knight of the Rose Croix of H.R.D.M
 
Join Date: Jun 2013
Location: Druid central, just East of Pandy, Nr. Abergavenny, S. Wales, UK, 3rd rock from the Sun
Posts: 15,034
Default Re: Estimate vs Quote

aye ...... now't like family ...... total nightmare to deal with
__________________
If it's got tracks, wheels, t*ts, or an engine, at some point it's gonna give you trouble!!
To view links or images in signatures your post count must be 10 or greater. You currently have 0 posts.
Reply With Quote
  #9   IP: 78.147.3.167
Old 24-03-2018, 06:09 AM
Mintsauce's Avatar
Mintsauce Mintsauce is offline
Master of the Ninth Arch
 
Join Date: Feb 2011
Location: In the Grub Hut
Posts: 1,543
Default Re: Estimate vs Quote

Is 500 that much extra over and above the original quoted or in this case estimated price. I don't think I ever complete a job for the exact costing or time estimate. Some you win a bit some you lose a bit. You just need to avoid keeping on losing a bit

If there's extras of course that's great
__________________
One Wife, Livid.
Reply With Quote
  #10   IP: 86.153.6.246
Old 24-03-2018, 06:52 AM
pond digger pond digger is offline
Knight of the East and West
 
Join Date: Dec 2010
Location: East Yorks
Posts: 2,408
Default Re: Estimate vs Quote

As others have said, a quote amounts to a legally binding contract. An estimated is a best guess.
Reply With Quote
Reply

Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump

 
Partner Links



All times are GMT +1. The time now is 02:27 AM.


Powered by vBulletin® Version 3.8.4
Copyright ©2000 - 2018, Jelsoft Enterprises Ltd.